How long does it take to build an ADU?
Construction takes three to four months once the permit is issued. Design and the permit come first, and permit time depends on your city and its review queue. Answered by MNBE founder Aharon Ben Elisha.
The Short Answer
Three to four months once the permit is issued.
Construction takes three to four months once the permit is issued, from the foundation to the final inspection.
Design and the permit come before that. In Seattle, plan review typically runs three to six months and depends mostly on correction cycles, and most ADU and DADU projects take eight to fourteen months in all, from first call to certificate of occupancy. Each city has its own rules, and you can compare them in our ADU rules by city. We prepare and submit to your city, answer every plan check correction ourselves, and schedule the inspections. What we build is on our ADU and DADU page.
The order of the work
Our builds follow the same phases: foundation, framing, roof, windows and exterior, then the inside. The table below shows that order with the real stage names from two of our builds: the Kirkland DADU, under construction now, and the Magnolia DADU, finished in 2026. You can also watch the builds.

Kirkland · Magnolia
Two builds, by the numbers.
Every stage has its own job-site photos on the Kirkland DADU and Magnolia DADU project pages.
Stage by Stage
The order of the work.
The stage names below are the ones on our project pages. The Kirkland rows run from excavation to the insulation. The Magnolia rows show the roofing, the exterior and the finish work, on a build that is finished.
| Stage | What happens | See it on |
|---|---|---|
| Before construction | ||
| Design | Architectural and structural drawings for your lot. | Permits & design |
| Permit | We prepare and submit to your city, answer every plan check correction ourselves, and schedule the inspections. | ADU rules by city |
| Foundation, framing, windows, siding, rough-ins and insulation · Kirkland DADU | ||
| Excavation | A mini excavator digs the footprint. | Kirkland DADU, stage 01 |
| Footing forms set, rebar in the forms | Footing forms are squared and braced along the trenches. Rebar is bent and tied through the footing runs, ready for the pour. | Kirkland DADU, stages 02 and 03 |
| Foundation poured | Footing and stem wall are poured together, in one pour. | Kirkland DADU, stage 05 |
| Underground plumbing | Waste and vent lines run below grade and stub up where the kitchen and the bathrooms land. | Kirkland DADU, stage 07 |
| Insulation + slab rebar, slab poured | Rigid foam boards go over the base, the slab rebar grid is tied above them, and the slab is poured. Foundation complete. | Kirkland DADU, stages 08 and 09 |
| Framing begins, walls go up | Layout on the cured slab: sill plates first, then the walls. On this two-story build the second floor goes on over the framed ground floor. | Kirkland DADU, stages 10 to 13 |
| Plywood sheathing | Plywood sheathing wraps the walls, with the window openings cut. | Kirkland DADU, stage 14 |
| Roof trusses set | The roof trusses are set on top of the second floor. | Kirkland DADU, stage 19 |
| Windows in | Black windows are in on both floors. | Kirkland DADU, stage 20 |
| House wrap, siding | Both floors are wrapped in house wrap, the weather barrier that goes under the siding. Then the siding panels go on over it. | Kirkland DADU, stages 21 and 22 |
| Plumbing, electrical and mechanical rough-in | While the walls are still open, the drain, vent and water lines run through the framing to each fixture, cable runs to a box for every outlet, switch and light, and the bath fans and their ducts go in the ceiling. Then the city inspects all of it before anything is covered. | Kirkland DADU, stages 23 and 24 |
| Insulation | Fiberglass batts fill the exterior walls and the ceiling under the roof trusses. Only after that do the walls close with drywall. | Kirkland DADU, stage 25 |
| Roofing, exterior and inside · Magnolia DADU | ||
| Standing seam metal roof | The metal roof is installed, with a skylight set into the panel pattern. | Magnolia DADU, stage 07 |
| Exterior wrapped | Fiber cement siding, windows and the glass garage door, all in place. | Magnolia DADU, stage 08 |
| Drywall hung, finish phase | Drywall hung, taped and mudded. Cabinets, bath and paint come next. | Magnolia DADU, stage 09 |
| Bathroom complete, exterior complete | Tile floor down and fixtures in. Siding painted, fence and gate finished. Handover ready. | Magnolia DADU, stages 10 to 13 |
| Final inspection | Aharon supervises each build through the final inspection. | Magnolia DADU |
Every photo on those pages is from the actual job site, taken by Aharon and his crew during the work.
Three stages, from our own job sites.
A foundation pour, a roof going on, and a finished exterior. Open a project to walk the whole build.
Reviews
What Seattle homeowners say about building with MNBE.
From our Google reviews.
"We hired MNBE Construction & Development for a full renovation of our 100+ year old home, and the results exceeded expectations. They handled full structural upgrades, … brand new insulation, … a luxury bathroom, a high-end kitchen, … a new roof, and mini-split AC units."
"My mom hired MNBE Construction for her two-bedroom DADU in Seattle, and watching the process up close was impressive. They did it all: design, architectural plans, the building permit, and the full construction. … The communication was excellent and there were never any surprises."
"We recently completed a DADU construction project in Seattle with MNBE Construction and Development LLC, and we couldn't be happier with the results. … The workmanship was excellent, communication was clear, and the entire process was handled professionally from start to finish."
Build time questions.
More answers: DADU vs attached ADU: which fits your lot? · Can an ADU be two stories? · How many ADUs can I build on my lot? City rules: Seattle, Bellevue, Kirkland and Redmond. All cities: ADU rules by city.
In Seattle, plan review typically runs three to six months and depends mostly on correction cycles. Other cities have their own review queues. We prepare and submit to your city and answer every plan check correction ourselves.
When the permit is issued. Design and the permit come first. Construction then takes three to four months once the permit is issued.
No. The footing and the stem wall are poured together, in one pour. You can see it on the Kirkland DADU page, at the stage called Foundation poured.
The roof, then the windows and the exterior, then the inside. On the Kirkland DADU the roof trusses were set once both floors were framed and sheathed, and the windows went in next. On the Magnolia DADU the metal roof went on first, then the siding, windows and garage door, then the drywall and the finish work.
It can. Seattle's pre-approved DADU plans have already been reviewed against the code, which can simplify plan review for your lot. Kirkland has pre-approved DADU plans and Renton offers permit-ready ADU plans.
Yes. The Kirkland DADU page grows with the project, and new stages get added as the work happens. The build films are on our videos page.
Tell us about your project.
We'll check your address against your city's ADU code and get back to you within one business day with a clear next step.
Contact information
Thank you for considering MNBE. Tell us your address and we will tell you, in writing, what your city's code allows on your lot. We respond within one business day, Sunday through Friday.