Everett ADU & DADU rules, in plain English
Short answer: Everett no longer has a separate ADU section. An ADU is a dwelling unit under 1,000 sq ft of interior habitable area, and it follows the same height, setback and coverage rules as the house in its zone. Up to two ADUs per lot get the city's ADU benefits. No parking is required, and the city has pre-approved DADU designs.
Written by MNBE founder Aharon Ben Elisha. Rules checked .
The Update
What changed in Everett.
Everett no longer has one ADU section. Ordinance 4102-25, passed June 18, 2025 and effective July 8, 2025, repealed the stand-alone section, EMC 19.08.100. Since then an ADU is treated as a small dwelling unit, and the general zone rules apply. The ADU label still matters for fee reductions, frontage improvements and the NR-C density rule.
Ordinance 4156-26, effective February 7, 2026, amended the sections that hold the ADU definition and the parking exception. The city also publishes an ADU handout and an ADU page.
Everett's pre-approved DADU designs
Everett runs a Pre-Approved Designs program, built on its Residential Basics program, with a gallery of pre-approved DADU designs. There were three designs in the gallery on the day we checked. The plans are already reviewed for the building and planning codes, and site-specific permitting is still required. How we build from a city's pre-approved plan is on our pre-approved DADU plans page, which covers Seattle's program.
Planning to build? See our Everett ADU and DADU builder page and how we build detached ADUs (DADUs). Rules for other cities are in our ADU rules by city guide. Nearby: Lynnwood ADU rules, Edmonds ADU rules and Bothell ADU rules.
Everett · Everett Municipal Code
Everett's ADU rules, by the numbers.
The four numbers homeowners ask about first. Check them against your lot with a feasibility study →
The Code
Everett ADU rules, line by line.
The NR, NR-C and UR4 zones. Zone-specific numbers vary, so we confirm them for each lot.
| Rule | What Everett allows | Source |
|---|---|---|
| ADUs per lot | Up to two ADUs per lot, attached or detached, receive the ADU benefits: fee reductions and no frontage improvements. In the NR-C zone the code permits up to two ADUs per lot, exempt from that zone's density limit. For the NR, UR and MU zones the city's ADU page says there is no limit to the number of dwelling units that may be developed on a lot if the general rules are met. | EMC 19.06.110, City ADU page |
| Size | Under 1,000 sq ft of interior habitable area, including basements and attics but not including a garage or accessory structure. The same for attached and detached. No percent-of-house limit. The city's ADU handout words it as a maximum of 1,000 sq ft of gross floor area. | EMC 19.04.030, City ADU handout |
| Height | ADUs follow the principal building table: 35 feet in NR-C and NR, 45 feet in UR4 and 75 feet in UR7. In a historic overlay, UR4 is limited to 38 feet. | City ADU handout, EMC 19.22.020 |
| Setbacks | The same as for principal buildings. NR: front 10 feet, street side 5 feet, interior side 5 feet, rear 5 feet, and no rear setback on a lot with an alley. NR-C: front 20 feet, street side 10 feet, interior side 5 feet, rear 20 feet. UR4: no front setback, street side 5 feet, interior side 5 feet (10 feet next to NR), rear 5 feet, and none on a lot with an alley. | EMC 19.06.020 |
| Coverage | Lot coverage by buildings: 35 percent in NR-C and 50 percent in NR. In NR, a lot with two dwelling units gets an additional 5 percent, and a lot with three or more gets an additional 10 percent. | EMC 19.06.010 |
| Parking | None for an ADU. The code exempts dwelling units with less than 1,200 sq ft of gross floor area. Bicycle facilities are still required. | EMC 19.34.050 |
| Owner occupancy | Not required. A city staff memo dated August 27, 2026 says the city removed the owner occupancy requirement in 2023. | City staff memo, August 27, 2026 |
| Design | A new dwelling unit, including an ADU, with any facade within 30 feet of a public street must face the street and include one of the listed entrance types: projecting porch, engaged porch, dooryard, stoop or common entry. For those units the code also requires a ground floor finish level of at least 6 inches, a ground floor ceiling height of at least nine feet (waived by the planning director through July 30, 2027), a roof design element, and windows or entry doors on at least 15 percent of each street-facing facade. Each dwelling needs a private yard, 8 feet minimum in any direction and at least 80 sq ft, or a shared yard. Mostly interior conversions are exempt (EMC 19.08.010). | EMC 19.08.030, EMC 19.08.040, EMC 19.08.050 |
| Pre-approved designs | The city's Pre-Approved Designs program has a gallery of DADU designs, three on the day checked. The plans are certified through the Residential Basics program and reviewed for building and planning codes. The owner picks a design and contacts the listed designer to license it. Site-specific permitting is still required, and changes to a certified plan send it back to the standard permit process. | Pre-Approved Designs program, Gallery of Pre-Approved Designs |
| Rentals | Short-term rental is allowed in a dwelling unit with a city business license. One operator may run no more than two short-term rental sites, and guests may not exceed eight on a site, including a site with an ADU. Renting a whole dwelling unit needs three off-street parking spaces where the site has on-street parking in front, and four where it does not. | EMC 19.13.250, EMC 19.34.020 |
| Zones | The city's ADU page says ADUs are permitted in all zones except Light Industrial and Heavy Industrial. | City ADU page |
| Impact fees | Park impact fees are reduced by 50 percent for the addition of one or two ADUs to a lot with one or more principal dwelling units to remain. The city's ADU page says the transportation fee is waived for the first ADU and reduced 50 percent for the second, and the school fee is waived for ADUs. | EMC 19.53.060, City ADU page |
| Street improvements | Frontage improvements are not required for the addition of one or two ADUs to a lot with one or more principal dwelling units to remain. | EMC 13.68.020 (moving to EMC 13.68.024 under the land divisions ordinance adopted October 14, 2026) |
| Water and sewer | Each dwelling unit requires a separate metered water service. At the discretion of public works, a shared meter may be allowed for a unit within or attached to an existing one-unit dwelling, provided both units remain under single ownership. The city handout says detached ADUs require separate water services and meters. Sewer, per the handout: a dedicated side sewer connection, which may share an existing side sewer on the same property if under single ownership and the shared section is at least 6 inches in diameter. | EMC 14.16.430, City ADU handout |
| Walkway | The city handout calls for a 4-foot-wide hard-surface walkway from the ADU's front door to the public street. | City ADU handout |
| Historic overlay | Historical commission review applies to a detached accessory dwelling, and to an accessory dwelling when not located entirely within an existing principal dwelling. | EMC 19.28.080 |
Checked . Sources: EMC 19.04.030, EMC 19.06.110, EMC 19.06.010, EMC 19.06.020, EMC 19.22.020, EMC 19.34.050, EMC 19.34.020, EMC 19.08.030, EMC 19.08.040, EMC 19.08.050, EMC 19.13.250, EMC 19.53.060, EMC 13.68.020, EMC 14.16.430, EMC 19.28.080, Ordinance 4102-25, Ordinance 4156-26, City ADU page, City ADU handout, City staff memo, August 27, 2026, Pre-Approved Designs program and Gallery of Pre-Approved Designs. The online code is current through Ordinance 4203-26, passed September 16, 2026. A plain-English summary, not legal advice. The code governs, and we confirm it for your lot.
Free Estimate
Check these rules against your Everett lot.
Tell us what you are planning. We reply within one business day, Sunday through Friday.
Your Lot
How we check an Everett lot for an ADU.
In Everett an ADU follows the general rules of its zone, so the zone comes first. This is the order we work in.
Zone and overlays
We confirm your zone and check the lot for critical areas, shoreline rules and overlays, which can limit a lot.
Trees
Tree rules can limit a lot. We locate the trees on your lot before we place the ADU.
Fit the footprint
We test size, height, setbacks and lot coverage against your lot and its zone, and whether an existing building can be converted.
Utilities
We check the water meter, the side sewer and power. The city handout says a detached ADU requires its own water service and meter.
Design and permit
We draw the plans in house, submit to Everett, answer corrections and carry the project through inspections.
Reviews
What homeowners say about building with MNBE.
From our Google reviews.
"We hired MNBE Construction & Development for a full renovation of our 100+ year old home, and the results exceeded expectations. They handled full structural upgrades, … brand new insulation, … a luxury bathroom, a high-end kitchen, … a new roof, and mini-split AC units."
"My mom hired MNBE Construction for her two-bedroom DADU in Seattle, and watching the process up close was impressive. They did it all: design, architectural plans, the building permit, and the full construction. … The communication was excellent and there were never any surprises."
"We recently completed a DADU construction project in Seattle with MNBE Construction and Development LLC, and we couldn't be happier with the results. … The workmanship was excellent, communication was clear, and the entire process was handled professionally from start to finish."
Common questions about Everett's ADU rules.
Short answers from the code and the city's ADU pages. For your exact lot, call us or book the free site visit.
Up to two ADUs per lot receive the city's ADU benefits, attached or detached. In the NR-C zone the code permits up to two ADUs per lot (EMC 19.06.110). For the NR, UR and MU zones the city's ADU page says there is no limit to the number of dwelling units on a lot if the general rules are met.
Under 1,000 square feet of interior habitable area, including basements and attics but not a garage (EMC 19.04.030). The city's ADU handout words it as a maximum of 1,000 square feet of gross floor area.
No. The code exempts dwelling units with less than 1,200 square feet of gross floor area, so none is required for an ADU (EMC 19.34.050). Bicycle facilities are still required.
Yes. The city's Pre-Approved Designs gallery had three DADU designs on the day we checked. The owner contacts the listed designer to license a design, and site-specific permitting is still required.
Yes. The city handout says detached ADUs require separate water services and meters. A unit within or attached to an existing one-unit dwelling may be allowed to share a meter if both units remain under single ownership (EMC 14.16.430).
An ADU follows the setbacks for principal buildings (EMC 19.06.020). In the NR zone: 10 feet at the front, 5 feet at the sides and 5 feet at the rear, with no rear setback on a lot with an alley. In NR-C: 20 feet at the front and rear, 10 feet at the street side and 5 feet at an interior side.
No. Everett does not require owner occupancy. A city staff memo dated August 27, 2026 says the city removed the requirement in 2023.
Tell us about your lot. We check it against Everett's ADU rules.
Add the property address to your message. We'll check it against Everett's ADU rules and get back to you within one business day with a clear next step.